A.Evaluatephaseexitmilestonesusingsufficiencycriteria
B.Flexibleentryandexitcriteriatominimizescheduledelays
C.Qualitymeasuresreportedonlytotheprojectsteeringcommittee
D.Manyworkteamswithfewmemberstomaximizethenumberofdeliverablehand-offs
参考答案:A